Contracting Case Study - Former Factory Site
- Client: National House Builder
- Location: Former Factory Site in Worksop
- Project: Complete Site Clearance & Remedial Works Services
- Duration: 20 weeks
- Value: £700,000 lump sum contract
T&P Regeneration were appointed to provide a “turnkey” package to convert a former factory into a site suitable for residential properties incorporating gardens.
The scope of the works included:
- production of a suitable Remedial Strategy, using third party investigation data to obtain approval from the Regulatory Authorities;
- procurement and management of the production of Type 3 asbestos survey report;
- removal of all the asbestos material from within the building followed by controlled demolition including dismantling a 40m high brickwork chimney;
- crushing of concrete arisings to produce 6F2 general fill material;
- excavation and removal of hydrocarbon and metal impacted soils to a suitably licensed landfill facility;
- Phased hand back of the site to suit the developers build programme;
- Validation of the site upon completion of the works and obtaining regulatory “sign off”.