Contracting Case Study - Former Factory Site

  • Client: National House Builder
  • Location: Former Factory Site in Worksop
  • Project: Complete Site Clearance & Remedial Works Services
  • Duration: 20 weeks
  • Value: £700,000 lump sum contract

T&P Regeneration were appointed to provide a “turnkey” package to convert a former factory into a site suitable for residential properties incorporating gardens.

The scope of the works included:

  • production of a suitable Remedial Strategy, using third party investigation data to obtain approval from the Regulatory Authorities;
  • procurement and management of the production of Type 3 asbestos survey report;
  • removal of all the asbestos material from within the building followed by controlled demolition including dismantling a 40m high brickwork chimney;
  • crushing of concrete arisings to produce 6F2 general fill material;
  • excavation and removal of hydrocarbon and metal impacted soils to a suitably licensed landfill facility;
  • Phased hand back of the site to suit the developers build programme;
  • Validation of the site upon completion of the works and obtaining regulatory “sign off”.